Order Capacity & Deadline is a yes/no on pooled printer hours versus the due date. It is not a job queue.

It adds up printers × hours you actually print per day and compares that to the work in the order. That answers “is this deadline even in the realm of possible?” — not “which machine starts at 7 p.m. Tuesday.”

If it does not fit, do not promise that date. Reduce quantity, add hours, or see Rush Order if you are considering a paid scramble.

Print Farm Capacity is different: remaining farm throughput over a week or month, including work already committed. Multiple Printer Manager assigns specific jobs to named printers. Bulk Order Planning turns one large order into plates and hours without a customer price.

One printer still works here: the pool is just that one machine’s hours.